The construction of a photovoltaic park in Rrakull, Kavaja, is approved

The Council of Ministers has approved the construction of a photovoltaic power generation plant in the village of Rrakull, Synej administrative unit, Kavaja Municipality.
According to the government's decision, the plant will have an installed capacity of 95 MW and is expected to be built and put into operation within 36 months from the entry into force of the decision.
DECISION ON THE APPROVAL OF THE CONSTRUCTION OF A PHOTOVOLTAIC ELECTRICITY GENERATION PLANT AND AUXILIARY WORKS, WHICH IS NOT A CONCESSION OBJECT, IN CADASTRAL ZONE 3204, VILLAGE OF RRAKULL, ADMINISTRATIVE UNIT OF SYNEJ, MUNICIPALITY OF KAVAJE, TIRANA DISTRICT, BY THE COMPANY “SELECT ENERGY”, LLC
In accordance with Article 100 of the Constitution and point 1, Article 49, of Law No. 43/2015, “On the Electricity Sector”, as amended, upon the proposal of the Deputy Prime Minister and Minister of Infrastructure and Energy, the Council of Ministers
1. Approval of the construction of the photovoltaic power generation plant and ancillary works, which is not subject to concession and does not benefit from support measures, located in cadastral zone 3204, Rrakull village, Synej administrative unit, Kavajë Municipality, Tirana District, by the company “SELECT ENERGY”, sh.pk, with the elements as follows:
a) Name of the applicant: “SELECT ENERGY” Company, sh.pk;
b) NIPT/NUIS: M22415014G;
c) Type of plant: Photovoltaic;
ç) Installed capacity: 95 MW;
d) Expected deadline for commissioning and issuance of a construction permit: The time for construction, issuance of a construction permit and commissioning of the photovoltaic plant will be within 36 (thirty-six) months from the entry into force of this decision;
dh) Location of the energy generating source: in cadastral zone 3204, Rrakull village, Synej administrative unit, Kavajë Municipality, Tirana District;
e) Operation period: 49 (forty-nine) years from the entry into force of this decision;
ë) Land coordinates and zoning plan, according to Annex 1, attached to this decision;
f) The Ministry of Infrastructure and Energy and the National Agency of Natural Resources have the right to exercise general supervision with 3-month deadlines during the implementation, commissioning and operation, with the aim of verifying that the progress of the works, quality, conformity and operation are in accordance with the general implementation program and project documentation;
g) The company “SELECT ENERGY”, sh.pk, has the obligation to: i. periodically (every three months), to the Ministry of Infrastructure and Energy and the National Agency of Natural Resources, information on the progress of the construction of the photovoltaic power plant; ii. to respect the conditions cited in the permits, licenses and preliminary environmental authorizations, issued by the institutions
responsible national;
iii. to submit the contract security, in the amount of not less than 5% of the investment value, before signing the contract between the company “SELECT ENERGY”, sh.pk, and the ministry. This contract defines the rights and obligations of the parties for the implementation of this project, penalties, in case of non-implementation, as well as other issues related to its implementation;
iv. to provide free of charge, in the form of royalty, to the ministry responsible for energy the amount of electricity, in the amount of 2% of the annual amount of electricity production or its conversion into monetary value. In case of conversion into monetary value, the amount must be paid entirely to the state budget;
v. to fulfill the request, as the case may be, that a part of the production of the energy generating source be sold to the public supplier, according to the legislation in force. 2. The Ministry of Infrastructure and Energy and the company “SELECT ENERGY”, sh.pk, are charged with the implementation of this decision.
This decision shall enter into force immediately and shall be published in the “Official Gazette”.
PRIME MINISTER
EDI RAMA
Happening now...
The revolution is over, Edi Rama continues calmly
ideas
top
Alfa recipes
TRENDING 
services
- POLICE129
- STREET POLICE126
- AMBULANCE112
- FIREFIGHTER128